Enabling a “faster, cheaper and safer” seismic survey for DNO

14th Mar, 2023
Project snapshot
About

Project snapshot


Client: DNO

Seismic contractor: GGFZCO

Goal of the seismic survey:

  • A seismic survey was required to obtain a 3D image of the subsurface for oil exploration and well-planning purposes.
  • The data acquired during this survey will be used to inform drilling decisions for an upcoming drilling campaign by DNO in the summer of 2023, in Northern Iraq.
  • The project had quick turnaround requirements, meaning the acquisition and processing needed to be fast-tracked to support well planning for 2023. With this being the case, DNO recognised they needed to look at alternatives to the cabled receiver technology traditionally used in the region to acquire seismic and to take new approaches, in order to achieve the desired efficiency rates, trace density, and data quality required to create a high resolution 3D seismic image.

Survey information

Untitled design 45

Location

Northern Iraq

C9b37bb1 e9ba 42e6 87ae fb71b43a37ed STRYDE Icon Low Environ Footprint

Survey terrain

Arid, mountainous region with gullies and rivers

Dbdcf83c 1cd0 4ae4 9c4d dbedef7f26c2 STRYDE Icon Dynamic

Survey size

250km2

66d1fd78 861c 41c7 bcc3 312564a15fbe Global Deploy Node

Number of nodes deployed

47,427 receiver locations were recorded in total over the 28 days of acquisition period.

Untitled design 47

Survey layout

Pseudo orthogonal survey design over~250 km2:

  • Receivers: 200m line spacing, 25m receiver point interval (47, 427 stations in total)
  • Source: irregular geometry with nominal 400m line spacing at 25m shot point interval. Source lines followed ridges within the complex terrain (26,153 source points acquired in total)
Icons 8

Source used

Vibroseis was used as the energy source for this project, with source points restricted to accessible terrain. Daily source productivity exceeded expectations. The maximum daily production achieved was >1500 shots, and the average was 930 shots per day.

Increasing receiver density on this project allowed DNO to deliver high data quality with reduced source effort. Avoiding dynamite source operations saved money and time, with vibroseis-only operations resulting in production rates at least 3x those of previous projects.

Be44540b d88e 4b08 b311 0dbdfbc12028 STRYDE Icon Respectful

Deployment and retrieval statistics

6 teams of 3 people were able to deploy sufficient nodes in the field to start source acquisition within 5 days of the first node being deployed. The active spread contained up to 19,000 nodes and was deployed within 5 days, allowing source acquisition to begin within 1 week of production activity starting.

After the recording was completed, 6 teams of 2 people retrieved the nodes in just 6 days.

In comparison to conventional seismic surveys of a similar size and complexity using cabled geophones, the client noted that the receiver deployment and retrieval crew size was more than 50% less on this survey even though the receiver density was double that of previous surveys (a 25m receiver point spacing was used for this survey vs 50m on previous cabled surveys).

How we helped

The technology we supplied

STRYDE supplied DNO and its seismic contractor with 22,000 STRYDE Nodes™, plus all field peripherals needed to deploy and retrieve the nodes efficiently and effectively. These included node deployment backpacks, navigator tablets loaded with the STRYDE Navigator software.

The STRYDE Nimble System ™ was supplied for this project for node charging, data harvesting, and seismic deliverables creation.

The technology we supplied

Survey challenges

Discover the challenges experienced during survey planning and how STRYDE technology helped overcome these challenges...

Ccac05ea c34d 4d9e bb73 9d0de48697e9 STRYDE Icon Improved Image Quality

Challenging terrain

The terrain was mostly made up of gullies, mountains, and rivers and required extensive pre-planning to ensure the vibroseis trucks could access lines and operate safely. To minimize any further pre-planning requirements and deployment time, it was crucial to identify receiver technology that was easy to transport and quick to deploy on foot.

Icons for Geo India 10

Permitting

An Environmental Impact Assessment (EIA) had to be completed prior to the survey being sanctioned. DNO had to specify the technology they planned to use and showcase how they would minimize environmental footprint and land disruption in the local area, and on farming operations and infrastructure.

Icons 11

A tight project turnaround

To achieve DNO’s operational plans for drilling the next well in their licensed area it was essential to reduce the seismic project turnaround time to pinpoint the best drilling location and fast-track decision-making.

Icons 10

Risk of equipment theft

Despite theft being common in the region, only 3% of nodes were lost but at no detriment to the final image quality and no NPT to replace lost or damaged equipment.

Icons 12

Weather

At the time the survey was due to commence, daytime temperatures exceeded +40°C and the extreme heat was expected to impact the ability of the crew to carry and deploy equipment in the field. DNO needed a lightweight receiver solution that was easy to carry and deploy. Seasonal rains and winds were also expected towards the end of the survey, so every effort was made to complete operations before the rainy season started, due to the risk of weather standby and additional noise..

Due to the increased operational efficiency of the nodal survey, DNO were able to expedite its program and only experienced 2 days of total downtime due to weather and GNSS challenges.

“Most onshore seismic surveys completed by DNO have used cabled geophones to record seismic data and in my experience, a similar survey of this size and complexity using cabled receivers would have taken 2-3 times as long to complete.

After seeing how efficient the STRYDE system is, and the cost savings we can make without compromising the seismic data resolution, I very much doubt we will ever use cabled systems again!

Using STRYDE technology has given us the confidence we needed to be more ambitious and go for higher density seismic acquisition, and I look forward to seeing what we can achieve on our next seismic survey.”

Jurgen Hoffmann

Geoscience Manager at DNO

waves

Benefits of working with STRYDE

The use of STRYDE Nodes™ on this acquisition enabled a magnitude of cost savings and operational efficiency gains, as well as reduced exposure to HSSE risk, and a significant reduction in environmental footprint and land disruption.

66d1fd78 861c 41c7 bcc3 312564a15fbe Global Deploy Node

Rapid equipment deployment of a high-channel count system

22,000 STRYDE Nodes™ were prepared and readied for shipment immediately upon contract signature enabling DNO to avoid any delays to the start of seismic acquisition and comply with the overall project timeline.


F9d7a6bf b89b 4297 b063 d0b541e74402 STRYDE Icon Reduced Cost

Access to high-resolution data, faster than ever before

High-resolution seismic data was acquired over an area of 250skm2 in just 28 days, allowing DNO to speed up the acquisition program and deliver processing-ready seismic data faster than ever experienced before. DNO received a fast-track 3D image ~4weeks after the final shot, and the fast-track results were of sufficient quality to start well planning immediately.

Icons for Geo India 10

Fast receiver deployment

DNO noted that the STRYDE system was very easy to use and the layout of the nodes was extremely fast-paced. Deployment was 3 times faster with STRYDE when compared to a similar sized survey using conventional cabled geophones. Source acquisition was able to start within days of the first node being deployed.

9ef2abf3 f7cb 4431 846f c12bebff7b6e STRYDE Icon Improved HSSE

Zero HSE incidents

Using lightweight modern receiver technology means that fewer vehicles and crew are needed for less time in the field, resulting in less HSE risk exposure. DNO reported zero HSE incidents during the seismic operations.

Icons for Geo India 5

Significant CAPEX and OPEX savings

The per-channel cost of STRYDE seismic systems is at least half that of any other seismic system in the world. Added to this, the operational efficiency of STRYDE systems means that project cycle time can be reduced simultaneously with running a smaller crew with fewer vehicles and reduced logistics effort, all of which contributes to a significant reduction in the overall cost to acquire the survey.

9c3eeeb1 bc31 45ed 829c 2e5e18b10298 STRYDE Icon Responsible

Project approval

Use of STRYDE’s inobtrusive receiver technology meant there would be minimal land disruption and environmental footprint. This supported the permitting process and helped ensure the seismic survey could commence in the desired location.

17badc04 be63 4aed b804 ebc9bbd0a14b STRYDE Icon Innovation

Removal of unnecessary and time-consuming tasks

Use of nodes reduced the need for line checks and eliminated technical downtime. Previous cabled system operations required time-consuming troubleshooting every day in difficult terrain to deal with theft and damage of system equipment. The customer noted that about 2 hours of productivity was gained each day through the use of nodes rather than cables by avoiding technical downtime. This time saving contributed to significant improvements in productivity and accelerated delivery of the overall seismic programme.

“This survey enabled by STRYDE Nodes™ was fast, efficient, and reliable. It delivered what we needed, and the data acquired was comparable with cable system data.

I am extremely impressed by the operational efficiency gains we were able to experience. Fast, cheap, and safe, with zero compromises on data quality is how I would summarise our experience.”

Jurgen Hoffmann

Geoscience Manager at DNO

waves

Discover our land seismic acquisition technology

The world needs high-density seismic imaging – but bulky, expensive equipment was stalling progress. That’s why we created the world’s smallest, lightest autonomous node.